September 16th, 2025 - 05:12 GMT
Azizi Developments, a leading private developer in the UAE, has announced that construction at Creek Views III, its luxury development on the shores of the iconic Dubai Creek in Dubai Healthcare City, has now reached 41%. The project remains on track for its delivery in Q3 2026. Structural works have been completed, while blockwork and internal plastering stand at 81% and 35% respectively. Tiling, MEP, and HVAC activities are progressing at 2%, 42% and 44%, with elevator installations at 1% and overall finishes at 19%. A total of 481 personnel ...